GENERAL INSTRUCTIONS
- No More Scale should be added at the start of the season during spring open up.
- Calculate the required amount from the dose rate below.
- Ensure that the pump and filter are running as normal.
- Mix the calculated dose in a clean bucket with water and evenly distribute around the pool. DO NOT ADD VIA THE SKIMMER SYSTEM.
- Filter as normal.
DOSE RATES
Initial & Final = 500mls per 50,000 litres of pool water
Monthly Maintenance = 100ml per 50,000 litres of pool water
After the Initial Dose has been added continue to apply the product on a monthly basis to ensure constant scale protection all year round. To remove discolouration on waterline tiles, raise the water level above the waterline level and maintain for at least 3 weeks.
A final treatment is recommended when the pool is winterised or will be idle for a long period of time. The main causes of scale formation are generally high levels of calcium and poor water balance, metal stains form due to incorrectly balanced water.